The molding is done

Woodmasters was able to expedite the planer parts (they arrived Friday), so we were able to get the molder working again and all the baseboard run! It looks really nice! Mike called Stairway Solutions and they can fit us in on Wed and Thurs, so we are very happy about that. :)

The kitchen is really coming together....and actually....Dennis is running out of things to do. He doesn't want to place the dishwasher and refrigerator until the floors are protected, and he cannot install the cooktop and downdraft until the granite is installed....so he's running out of things to do. He finished the downdraft duct work and is nearly finished with the crown molding above the cabinets.

Bissell Jr was able to find matching stain, and Judi came by and approved the color...so we're on our way with that too. Also, Marble and Granite Works made their templates and will be calling us soon to approve the slabs and template placement.

We are very pleased with the progress thus far!

Comments: Post a Comment

<< Home

This page is powered by Blogger. Isn't yours?